Work is underway to improve the detour route used when State Highway 2 at the Waiotahe Bluffs is closed, to create a safer resilience connection to Ōpōtiki and beyond.
Ōpōtiki District Council is making progress toward widening 15 locations along Waiotahi Valley Back Road, Verrall Road and Paerata Ridge Road, as well as improving the Verrall Road and Paerata Ridge Road intersection and a corner on Waiotahi Valley Back Road.
The improvements will make it easier and safer for vehicles, including heavy trucks, to use the route when closures of SH2 require traffic to be diverted.
Ōpōtiki District Council, Group Manager Service Delivery Nathan Hughes says over the last three years the Waiotahe bluffs closed several times due to landslips alone, resulting in long closures of the State Highway. When these closures occur, there are a range of safety concerns with heavy vehicles using our local roads, so getting the funding for this project was something we wanted to secure this year.
“We’re pleased that Council has been able to secure over 70% of funding externally from Waka Kotahi New Zealand Transport which is allowing us to break ground this side of Christmas,” Mr Hughes said.
"When the bluffs close, our local roads are our only connection route for the community, commuters, visitors, businesses and freight. This work is about making sure the alternative route can function as effectively and safely as possible when we need.
"Widening key sections and improving some of the more challenging corners and intersections will make a real difference, particularly when larger vehicles are using the route. It's a practical investment that will help keep people and goods moving when State Highway 2 isn't available,” Mr Hughes said.
Early works have begun, with Council's road maintenance contractor carrying out shoulder and vegetation clearance.
Main works are planned to take place between January and May 2027 and the route will remain open throughout the works, however motorists should expect short delays around individual worksites.
Mr Hughes says Council appreciates the patience of road users and people living along the route while the improvements are carried out.
"There will be some short-term disruption while the work is underway, but the end result will be a more resilient and fit-for-purpose alternative route. We appreciate everyone on these local roads, taking a little extra care around the crews and maybe allowing a bit more time for their journey," Mr Hughes said.
Residents were encouraged to view the project page on council’s engagement website Hono Mai | Connect earlier in the week and wider community access is being promoted from today.
Visit connect.odc.govt.nz